New Pool Construction Project in Waxhaw
The steel erection phase and rough plumbing for this project are now complete. A 4″ gravel base was spread on the bottom of the pool to keep the area clean and to provide a good foundation for the concrete shell. 3/8″ rebar was used on the walls, while 1/2″ rebar was used on the floor, […]
New Pool Construction Project in Stonegate
The concrete shell installation was completed last week. We shot the pool shell using 4,000 psi shotcrete, which is a mixture of portland cement, aggregate (rock) and water all mixed together and pumped from a concrete truck’s barrel mixer to a concrete pump. The shotcrete is pumped through a 2 1/2″ hose that has a […]
New Pool Construction Project in Stonegate
Construction is underway at this new pool project in the Stonegate neighborhood of Charlotte. Here are a couple of before photos…
Several trees and plants were removed or transplanted prior to the start of the dig.
Continue Reading →